2016 End of Year Updates
/** * Meta info (Date, Author, etc) for the Loop */ ?>Detailed Structural Work By: Construction Project Manager, Ken Potter This fall the workers were preparing for and adding additional columns … Continue reading
Detailed Structural Work By: Construction Project Manager, Ken Potter This fall the workers were preparing for and adding additional columns … Continue reading
By: Ken Potter, REVOLUTION Construction Manager The REVOLUTION Tour is completed, what an amazing experience. Over one month ago Stacy … Continue reading
The REVOLUTION Update Tour is wrapping up with the last few stops this week! We are so grateful for Construction … Continue reading
The REVOLUTION Update Tour continues as well as the construction work onsite in the DR! We are so grateful for … Continue reading
By: Ken Potter, REVOLUTION Construction Manager Fall is here – it is a beautiful cool evening here! It has been raining … Continue reading
By: Ken Potter, REVOLUTION Construction Manager Construction has progressed the past month getting columns formed and many plumbing pipes installed. … Continue reading
By: Ken Potter, REVOLUTION Construction Manager The project construction has made great progress this summer. After laying almost 70,000 block, … Continue reading
By: Ken Potter, REVOLUTION Construction Manager It’s August 2016 and we have walls! Last week the plumbing workers started installing … Continue reading
The REVOLUTION Update Tour is coming back to a location near you! REVOLUTION Construction Manager, Ken Potter, will be traveling … Continue reading
By: Ken Potter, REVOLUTION Construction Manager 70,000 block are now onsite and most are laying in walls! Our three mason … Continue reading